SoftBank loses $3.7bn on power kit: AI orders are not firm
SoftBank has written off $3.7bn in deposits for power-generation equipment after changing its plans for American data centres. The group reported a net loss of ¥1.1trn, about $7bn, for July to September.
One of the most aggressive buyers of turbines and transformers for AI data centres has withdrawn orders and accepted the loss of its deposits. Full order books at suppliers are not the same as secure revenue.
What happened
Data centres need power, and gas turbines, transformers and switchgear have long lead times. Developers have therefore ordered early and paid large deposits. SoftBank says it made such advance payments to guard against shortages. After reviewing its projects it is pulling out of part of the contracts. The deposits were non-refundable and fees were added. According to Reuters this includes a large project in Pike County, Ohio. The chief financial officer, Yoshimitsu Goto, said some equipment was no longer the best fit and that he could not promise it would not happen again.
SoftBank stresses that it is not shrinking current projects. According to Reuters it is entitled to rebates of up to $2.1bn on future purchases. Financing costs more than doubled in the quarter. Results were also weighed down by losses on holdings; according to Reuters the share price has almost halved since early June.
What follows
For makers of power-generation and grid equipment, including European suppliers of gas turbines and grid components, the value of their order backlog changes. When large developers rework orders, suppliers keep deposits, but factory capacity and staffing rest on orders that are not firm. According to Bisnow, shares in American suppliers such as GE Vernova and Bloom Energy fell after the news. For banks and investors financing data centres and their power supply, exit clauses and advance payments move to the fore. Assessment: one buyer does not prove a turn; SoftBank also cites technical reasons for changing equipment. For suppliers in German-speaking Europe hoping to profit from data-centre power demand, the quality of the order book matters more than its size.
What changes in practice
- Suppliers
- Deposits protect against losses but not against idle production lines when customers rework orders.
- Investors
- Large backlogs in AI power equipment include orders that buyers can withdraw at the cost of their deposit.
- Banks and lenders
- In loans for data centres and their power supply, exit clauses and advance payments carry more weight.
What to watch
- Order intake and cancellations at power and grid equipment makers in coming quarterly results
- Further write-downs of deposits by data-centre developers
- Progress of the projects in Ohio and Texas
Sources
- Reuters via The Star: SoftBank books $7 billion quarterly loss on US data centre hit
- Bisnow: SoftBank takes $3.7B hit on data center equipment it no longer wants
- investingLive: SoftBank swings to $7 billion Q2 loss on $3.7 billion US data centre power hit
- SoftBank Group: Earnings Results Briefing for Q2 FY2026